McWilliams Road

Phase 1

Phase 1 involved land acquisition, survey, and engineer design. All was completed and the bid for construction went out in December 2023.

Phase 2

Phase 2 involves construction. Estimated 90-day project.
9/24/2024 Road completed and open.
8/29/2024 Road completed, fencing completed, waiting on signage.
8/19/2024 Paving of road completed.
8/1/2024 Curb & gutter completed.
7/24/2024 Curb & gutter under construction.
7/16/2024 The 10 ft pedestrian path (ashalt) constructed.
6/27/2024 Dirt work complete, retaining wall constructed, curb & gutter started.
6/11/2024 Road elevation and compaction completed.
5/30/2024 Contractor has mobilized, road staking and dirt work is underway.



Last Updated 9/24/2024
Paving completed.
Road completed, waiting on signage and striping.
Paving completed.
Paving of road completed.
Curb & gutter completed.
Curb & gutter completed.
Curb & gutter under construction.
Curb & gutter under construction.
Pedestrian path completed.
Pedestrian path constructed.
Dirt Work completed
Dirt work complete, retaining wall constructed.
Dirt work underway
Road elevation and compaction completed.
Road work has commenced
Contractor has mobilized, road staking and dirt work is underway.
McWilliams Road