Phase 2
Involves some additional infrastructure to North Main. This includes:
• Restroom (COMPLETED).
8/15/2024 |
Installation of sidewalks completed. |
8/7/2024 |
Installation of vault restroom completed. |
8/6/2024 |
Excavation of the restroom vault pit has begun. |
• Hampton Culvert.
|
The crossing of Hampton Canyon Arroyo has been delayed due to fund shortage. |
• Lift/Pump Station.
|
Wet well designed for maximum size is in the process of being ordered. |
|
The pump system will be ordered once development begins. |
Last Updated 1/8/2025