North Main Extension (Phase 2)

Phase 2

Involves some additional infrastructure to North Main. This includes:
  • • Restroom (COMPLETED).
  • 8/15/2024 Installation of sidewalks completed.
    8/7/2024 Installation of vault restroom completed.
    8/6/2024 Excavation of the restroom vault pit has begun.

  • • Hampton Culvert.
  • The crossing of Hampton Canyon Arroyo has been delayed due to fund shortage.

  • • Lift/Pump Station.
  • Wet well designed for maximum size is in the process of being ordered.
    The pump system will be ordered once development begins.


    Last Updated 1/8/2025
    Restroom
    Restroom project completed.
    2024-08-07a
    Restroom: Vault being installed.

    North Main Extension