South Aztec Water System
Phase 1. Water System Design and Engineering.
• City has contracted an engineer firm to prepare Preliminary Engineering Report (PER) and then move into complete engineering design once funding is obtained.
Phase 2. Reconstruction of Bladder Tank.
• Funding has been acquired.
• Bladder tank will be replaced with above ground tank storage.
• Design completed.
Phase 3. Reconstruction of 12" water line from Aztec to Bloomfield.
• Funding for design aquired.
• Memorandum of Understanding with Bloomfield completed.
Phase 4. Upgrading of service lines within the South Aztec water service area.
• Seeking funding assistance.
Last Updated 6/17/2025