Main Avenue Courtyard

The City received grant funding from the NM state legislatures for plan, design, and construction of downtown Main Ave. That funding was used to refurbish the Main Avenue Courtyard located at 114 S. Main Ave.

Phase 1 (Demolition)

City staff removed the current brick pavers of the courtyard.
Completed in February 2024.

Phase 2 (Utilities)

The Aztec Electric Department will rebuild the electric infrastructure within the courtyard to provide better lighting and outlet access. The Parks & Recreation will redo irrigation to planters.
Completed in March 2024.

Phase 3 (Courtyard Surface)

The City has hired a contractor to resurface the courtyard with stamped concrete. The City opted for concrete as a paver surface was costly and from past experience caused issues with surface leveling and trip hazards.
Completed in May 2024.


Last Updated 5/15/2024
Work Completed
Courtyard is open.
Concrete Work Completed
Concrete work and lighting completed.
Concrete Work Underway
Concrete work is underway.
Concrete Work begun 2024-04-10
Concrete work has begun.
Utility Installation Complete
Utility installation complete, ready for concrete.
Trenching 2024-02-28
Trenching for utiltities underway.
Demolition 2024-02-20
Removal of courtyard pavers.
Main Ave Courtyard
Main Ave Courtyard prior to demoliton/construction.