The City received grant funding from the NM state legislatures for plan, design, and construction of downtown Main Ave. That funding was used to refurbish the Main Avenue Courtyard located at 114 S. Main Ave.
Phase 1 (Demolition)
City staff will remove the current brick pavers of the courtyard.
2/20/2024 |
Removal of pavers within the courtyard started. |
2/22/2024 |
Removal of pavers within the courtyard completed. |
Phase 2 (Utilities)
The Aztec Electric Department will rebuild the electric infrastructure within the courtyard to provide better lighting and outlet access. The Parks & Recreation will redo irrigation to planters.
2/26/2024 |
Trenching for utiltities completed. |
3/14/2024 |
Irrigation lines installed. |
3/20/2024 |
Utility lines and light bases poured/installed. |
Phase 3 (Courtyard Surface)
The City has hired a contractor to resurface the courtyard with stamped concrete. The City opted for concrete as a paver surface was costly and from past experience caused issues with surface leveling and trip hazards.
5/15/2024 |
Construction on Main Ave Courtyard is complete and the Courtyard is officially open. |
5/2/2024 |
Concrete work is done. Lighitng installed. Legacy bricks laid. Lack planting and mulching of the planters. Ribbon cutting for re-opening scheduled for May 18. |
4/08/2024 |
Concrete work is underway. The surface is a stamped sandstone with mottled coloring. |
Last Updated 5/15/2024