McWilliams Road

Phase 1

Phase 1 involved land acquisition, survey, and engineer design. All was completed and the bid for construction went out in December 2023.

Phase 2

Phase 2 involves construction. Estimated 90-day project.
Project was completed in October 2024.


Last Updated 11/18/2024
Paving completed.
Road completed.
Paving completed.
Road completed, waiting on signage and striping.
Paving completed.
Paving of road completed.
Curb & gutter completed.
Curb & gutter completed.
Curb & gutter under construction.
Curb & gutter under construction.
Pedestrian path completed.
Pedestrian path constructed.
Dirt Work completed
Dirt work complete, retaining wall constructed.
Dirt work underway
Road elevation and compaction completed.
Road work has commenced
Contractor has mobilized, road staking and dirt work is underway.
McWilliams Road