Phase 1
Phase 1 involved land acquisition, survey, and engineer design. All was completed and the bid for construction went out in December 2023.
Phase 2
Phase 2 involves construction. Estimated 90-day project.
8/29/2024 |
Road completed, fencing completed, waiting on signage and road striping. |
8/19/2024 |
Paving of road completed. |
8/1/2024 |
Curb & gutter completed. |
7/24/2024 |
Curb & gutter under construction. |
7/16/2024 |
The 10 ft pedestrian path (ashalt) constructed. |
6/27/2024 |
Dirt work complete, retaining wall constructed, curb & gutter started. |
6/11/2024 |
Road elevation and compaction completed. |
5/30/2024 |
Contractor has mobilized, road staking and dirt work is underway. |
Last Updated 8/29/2024