Phase 1
Phase 1 of the North Main Extension is complete. It involved the installation of utilities (electric, sewer, and water lines), curb and gutter, sidewalks, street paving, landscaping, remote parking area, plaza, and trail to Rio de Animas Park.
Phase 2
Involves some additional infrastructure to North Main. This includes:
• Restroom (COMPLETED).
8/15/2024 |
Installation of sidewalks completed. |
8/7/2024 |
Installation of vault restroom completed. |
8/6/2024 |
Excavation of the restroom vault pit has begun. |
• Hampton Culvert.
|
The crossing of Hampton Canyon Arroyo has been delayed due to fund shortage. |
• Lift/Pump Station.
|
Design for maximum size completed. |
|
The pump system will be ordered once development begins. |
Last Updated 6/17/2025