Phase 1 involved reconstruction and shot-concreting of the irrigation ditch lining along Reservoir #1. The irrigation lining was concreted, inlet reconstructed, and completed in 2023.
Phase 2 construction involved the concrete lining and tower rebuild within the reservoir.
10/03/2024 |
Reservoir #1 completed. reservoir filling up with water. |
9/25/2024 |
Reservoir #1 completed. Dedication Ceremony on 9/25/2024. |
9/5/2024 |
Reservoir construction completed, fencing near completion. |
8/19/2024 |
Sand zone completed, tower walkway installed, and maintenance road graveled. |
8/1/2024 |
Installation of reservoir lining completed and sand zone being added. |
7/24/2024 |
Installation of reservoir lining underway. |
7/16/2024 |
Installation of reservoir lining underway. |
7/3/2024 |
Ramp construction completed. |
6/10/2024 |
Ramp construction in underway. |
5/30/2024 |
Tower construction near completion, ramp construction underway. |
5/2/2024 |
Dirt work and ramp construction underway. |
4/4/2024 |
Lining and base prep underway. |
3/20/2024 |
Dirt work, shaping, and elevation marking underway. |
2/28/2024 |
Demolition of concrete liner completed. |
2/20/2024 |
Demolition begun. |
1/23/2024 |
The project was awarded. |