PROJECTS

Project 1. Aztec Disc Golf Course
Add three additional baskets to the 6-hole course. Involves digging holes and mounting the basket post in concrete. T-box frames will be constructed with 2x4s in the size of 4ft x 6ft. Excavate the turf to 3 inches down so that the T-box frames will sit at ground level surface. Fill frames with concrete. Install sign frame for sign panel showing the disc golf course.

Project 2. RV Parking Facilities
Install new post & cabling (560 feet / 28 posts). Install picnic tables (5) and electric pedestals (6).

Alternate 1. Riverside Post & Cabling Improvements
Identify posts that are not capped and install metal caps. Tighten all loose cabling around the park.

Alternate 2. Animal Shelter Dog Park Amenities
Hand excavate water line trench for frost-free faucet. Excavate pit to install 8' metal water trough for holding water. Construct steps to pavilion.

Alternate 3. Rio de Animas Trail Signage
Installation of 3 sign frames and sign panels.